Gravel Calculator

Gravel Calculator: Tons and Cubic Yards, Layer by Layer

A gravel calculator should answer the questions the quarry will ask: how many tons, how many yards, and which stone goes in which layer. Enter your areas and depths in feet and inches or metres and centimetres, and you get loose cubic yards or m³, US tons and metric tonnes per layer, an order rounded the way stone is sold, truckloads and cost.

Gravel calculator

Switching units changes the results and the empty fields; numbers you have typed keep their own units.

1 Area

Measure length and width in feet or metres. Round areas are measured across (diameter). Split an L-shape into rectangles and add each one.

    Total area: —

    2 Layers, bottom to top

    Start from:

      Enter the finished depth of each layer. Base stone settles under a plate compactor or roller, so the loose-to-compacted allowance is added to what you order: 8 in loose rolls to 6 in = 33 %.

      3 Order and delivery

      Ask your hauler what one load holds; tandem loads are usually quoted in tons.

      Enter the size of the area and the depth of each layer.

      Typical depths (finished, after compaction)
      Pea gravel path or patio2–3 in (5–8 cm) over a compacted base
      Gravel driveway, all layers4–6 in (10–15 cm): 3–4 in #3 base, 2–3 in #57, 1–2 in #8 or pea on top
      Farm lane with road-surface aggregate (DSA)6 in (15 cm) compacted from 8 in (20 cm) loose
      Thick basesCompact in lifts of no more than 6 in (15 cm)

      Heavier traffic and soft ground need more. These are typical figures; change them to suit your job.

      Measure the ground before you ring the quarry

      A gravel calculator is only as good as the three numbers you feed it. Length and width go in feet or metres. Depth goes in inches or centimetres: I measure depth in inches, never in feet, because a 4 left in a feet box orders twelve times the stone.

      • Rectangles (drives, parking pads, paths): length × width.
      • Round areas (fire-pit circles, tree rings): measure straight across. The tool asks for the diameter, because that is what your tape reads; a diameter typed into a radius formula gives four times the area.
      • Triangles (the flare where a drive meets the road, wedge corners): base × height ÷ 2.
      • L-shapes and turnarounds: split them into rectangles, circles and triangles and enter each as its own area. They add up into one order. An area you already know, from a plan or a survey, goes in as a single number.
      • Uneven ground: probe the dug-out bed or the old stone at five or six spots and use the average depth.

      Loose versus compacted: the step most calculators skip

      Stone arrives loose and gets thinner when you compact it. A crushed base with fines loses a fifth to a third of its loose depth under a plate compactor or roller, so a 6 in finished base ordered as 6 in of loose stone leaves you short. Order the base loose, not compacted.

      The Penn State Center for Dirt and Gravel Roads places driving surface aggregate (DSA) 8 in loose and rolls it to 6 in, or 6 in loose to 4½ in. That is 1⅓ times the compacted volume, a 33 % allowance. Their field check for a lane: tons = length (ft) × width (ft) × 0.04 at 8 in loose. Ohio DOT Item 411 caps a compacted lift of crushed aggregate at 6 in, so a thicker base goes down in lifts, each one compacted.

      Each layer in the calculator gets its own loose-to-compacted allowance. My starting points: 0 % for decorative cover nobody compacts, 10 % for pea gravel that settles under foot, 20 % for a plate-compacted crushed base, 33 % for dense-graded road base. A separate waste allowance goes on top, and the two multiply: 10 % and 5 % make ×1.155, not ×1.15.

      Eight inches of loose crushed stone compacted by a plate or roller into six inches of finished base
      8 in loose rolls down to about 6 in, so a compacted base needs a third more stone than its finished volume.

      The gravel calculator formula on real jobs

      Area: rectangle L × W · circle π × (D ÷ 2)² · triangle ½ × base × height
      Loose ft³ = area (ft²) × depth (in) ÷ 12 × (1 + compaction) × (1 + waste)
      yd³ = ft³ ÷ 27 · m³ = yd³ × 0.764555
      US tons = m³ × density (kg/m³) ÷ 907.185 · tonnes = m³ × density ÷ 1000

      A US (short) ton is 2000 lb, or 907.18 kg; a metric tonne is 1000 kg, about 10 % more. Most loose gravel runs 1.4–1.7 US tons per cubic yard, so one ton is roughly 0.6–0.7 yd³ (0.714 yd³ at 1.4). These are jobs I would actually price, each rechecked step by step:

      Worked examples (loose volumes, densities from the weight table below)
      JobInputsVolumeWeight
      Pea gravel patio 10 × 10 ft3 in, pea gravel 1680 kg/m³, +10 % waste100 × 3 ÷ 12 = 25 ft³ = 0.926 yd³; ×1.1 = 1.02 yd³1.31 → 1.44 US tons; order 1½ tons or 1 yd³
      Fire-pit circle 12 ft across3 in river rock 1650 kg/m³π × 6² = 113.1 ft² → 28.27 ft³ = 1.047 yd³1.46 US tons
      Farm lane 100 × 12 ftDSA 6 in compacted, +33 % (8 in loose), 1920 kg/m³1200 × 8 ÷ 12 = 800 ft³ = 29.63 yd³about 48 US tons; Penn State: 100 × 12 × 0.04 = 48
      Drain trench 50 ft × 1 ft18 in of #57 stone 1660 kg/m³75 ft³ = 2.78 yd³3.89 US tons
      Riprap on a bank 40 × 6 ft18 in riprap 2190 kg/m³360 ft³ = 13.33 yd³24.61 US tons
      Metric drive 15 × 3 mQP sub-base 15 cm +25 %; pea top 5 cm45 × 0.15 × 1.25 = 8.44 m³; 45 × 0.05 = 2.25 m³16.2 t + 3.78 t; top = four 1 t bulk bags

      The fire pit shows why the diameter matters: the same 12 typed as a radius gives 4.19 yd³ instead of 1.05.

      How much a cubic yard of gravel weighs

      One figure of 1.4 tons per yard for everything undercounts riprap and road base and nearly doubles lava rock. These are loose, dry, as-delivered densities; the tool starts from the default column and lets you type your yard's own number.

      Loose bulk density by stone (ranges from published supplier figures and the Penn State DSA bulletin)
      StoneDefault kg/m³US tons per yd³Typical rangeyd³ per US ton
      Pea gravel (⅜ in)16801.421.25–1.50.71
      Crushed stone #3, #57, #8; crushed limestone, granite, marble chips16601.401.4–1.70.71
      River rock (1–3 in)16501.391.3–1.60.72
      Crusher run / QP, DGA / DSA road base19201.621.5–1.70.62
      Bank / pit-run gravel19401.631.4–1.70.61
      Crushed slag17501.47varies by source0.68
      Lava rock8800.74ask the supplier1.35
      Riprap (4–24 in)21901.851.7–2.00.54

      Wet stone weighs more, and so does stone after compaction: Ohio DOT pays compacted crushed stone at 3800 lb per cubic yard in place, about 1.9 tons. Use that figure to check a finished base, never to order loose stone.

      How far a ton or a yard of gravel goes

      Coverage before any compaction or waste allowance
      Depthft² per yd³ft² per US ton at 1.4 t/yd³ft² per US ton of road base (1.62)
      2 in162115.7100
      3 in10877.166.7
      4 in8157.950
      6 in5438.633.3
      Metric coverage (pea gravel, 1680 kg/m³)
      Depthm² per m³m² per tonne
      3 cm33.319.8
      5 cm2011.9
      10 cm105.95

      Suppliers often quote 100, 80 and 60 ft² per ton at 2, 3 and 4 in. Those are rounded down from the exact figures and leave a sensible cushion.

      Building it up in layers

      A driveway that lasts is a stack, not a pile. On firm soil a typical build-up is 6–9 in in total: 3–4 in of #3 at the bottom, 2–3 in of #57 in the middle, 1–2 in of #8 or pea gravel on top. Heavier traffic or soft soil needs more. Pea gravel never goes under a driveway: round stones roll, and only angular crushed stone locks into a base. Give the finished surface a crown of ½–¾ in per foot so water runs off instead of sitting in ruts.

      The calculator lets you stack up to four layers, each with its own stone, density, finished depth and allowance. It draws the build-up to scale, with a ruler and a label on each layer showing the loose depth to order, so a wrong depth is visible at a glance. Presets cover a three-layer drive, a DSA farm lane, a garden path and a metric patio, all editable.

      Cross-section of a crowned gravel driveway: 4 in of #3 stone, 3 in of #57 and 2 in of #8 or pea gravel over compacted subgrade
      The three-layer drive from the example below, with the crown that sheds water.

      Worked example, a 60 × 12 ft drive (720 ft²):

      1. #3 base, 4 in, +20 %: 720 × 4 ÷ 12 × 1.2 = 288 ft³ = 10.67 yd³ → 14.92 US tons at 1660 kg/m³.
      2. #57 middle, 3 in, +20 %: 216 ft³ = 8.00 yd³ → 11.19 US tons.
      3. Pea or #8 top, 2 in, no allowance: 120 ft³ = 4.44 yd³ → 6.29 US tons at 1680 kg/m³.
      4. Total: 23.11 yd³ = 32.41 US tons. At an example price of 38 per US ton that is 1,231.49; with 14-ton loads it is 3 trucks, or 4 if each stone comes on its own truck.

      Stone sizes and where each belongs are in crushed stone sizes explained; the full driveway build, from subgrade to crown, is in gravel driveway layers; for garden work read pea gravel patios and paths.

      Driveways for heavy trucks, steep slopes, culverts, retaining walls and riprap on streams or shorelines are engineering and often permit matters. Treat these numbers as general information, follow local codes and ask a contractor or engineer.

      Ordering: tons or yards, rounding and truckloads

      Quarries weigh stone and price it per ton; many landscape suppliers load by the bucket and price per cubic yard. Ask which, and enter the price in that same unit. The tool takes a price per US ton, per metric tonne, per yd³, per m³ or per bag, and you set the currency sign yourself, so a price per short ton is never applied to tonnes, a 10 % error either way.

      Round up the way stone is sold: to the next ½ yd³ or to whole US tons, to whole m³ or whole tonnes, or to bags of a size you type (1000 kg by default, the usual 1 t bulk bag). Each layer is rounded on its own. The cost is worked out on the rounded order, which is what you will pay, or on the exact amounts when rounding is off.

      Truck capacity depends on the truck and on local weight limits, so ask your hauler for the number. I start at 14 US tons for a tandem (10 t in metric); the tool also takes a volume limit for light stone that fills the box first. Loads are rounded up: 28 tons in 14-ton loads is exactly 2 trucks, not 3. The tool also shows how many trucks you would need if every stone came on its own.

      Already have a pile? Open the What will it cover? tab and reverse the sum. Five US tons of crushed stone at 4 in covers about 289.5 ft²; 2 t of pea gravel at 5 cm covers 23.8 m². Give it the amount and your area instead, and it returns the depth.

      Mistakes I see on first gravel orders

      • Depth typed in feet, or a diameter typed as a radius (×12 and ×4 the stone).
      • Ordering a base by its compacted depth instead of its loose depth.
      • Mixing up US tons and metric tonnes: about 10 % off.
      • One "1.4 tons per yard" for everything: riprap and dense road base run 1.6–2.0, lava rock about half.
      • Laying a thick base in one lift. Compact in lifts of no more than about 6 in.
      • Round pea gravel as a driveway base: it rolls.
      • No crown, so water stands on the drive and softens the base.

      Behind the numbers: densities, rounding and test cases

      Every job is worked in metres internally, with exact unit factors: 1 ft = 0.3048 m, 1 in = 2.54 cm, 1 yd³ = 27 ft³ = 0.764554857984 m³, 1 US ton = 2000 lb = 907.18474 kg. Weight is loose volume × loose density; allowances multiply; results round only for display, and orders and truckloads always round up. Densities are the defaults in the weight table, set inside published ranges. Moisture and gradation move them, so use your supplier's figure when you have one: the density box takes kg/m³, US tons per yd³ or lb/ft³. Switching between feet and metres keeps what you typed, because each field remembers its own unit; only empty fields switch. A negative, non-numeric or absurdly large entry gets an error on that field and is left out of the result until you fix it. The calculator runs entirely in your browser and sends nothing anywhere; your last job is remembered in this browser only.

      I check the tool against cases worked out by hand:

      Control cases
      InputExpected result
      Rectangle 20 × 10 ft, 4 in pea gravel (1680), no allowances, example price 40 per US ton66.67 ft³ = 2.469 yd³ = 1.888 m³; 3.496 US tons = 3.171 t; cost 139.84. Rounded to ½ yd³: 2.5 yd³, cost 141.59; to whole US tons: 4, cost 160; in 1 t bags: 4 bags
      Rectangle 5 × 4 m, 10 cm crushed stone (1660)2.000 m³ = 2.616 yd³; 3.320 t = 3.660 US tons
      100 m² × 10 cm, then switch to feet and inchesstill 10 m³ = 13.08 yd³
      Circle 12 ft across, 3 in river rock (1650)113.10 ft²; 1.047 yd³ = 0.801 m³; 1.456 US tons
      Lane 100 × 12 ft, 6 in compacted, +33⅓ %, DSA entered as 120 lb/ft³ (1922 kg/m³)800 ft³ = 29.63 yd³ loose; 48.0 US tons (47.94 at the default 1920)
      Riprap 10 yd³ (2190); limestone 10 yd³ (1660)18.46 US tons = 16.74 t; limestone 13.99 US tons
      Three layers on 60 × 12 ft (example above), 14-ton truck, example price 38 per US ton23.11 yd³; 32.41 US tons; cost 1,231.49; 3 loads (4 with one truck per stone)
      10 m³, +10 % allowance, +5 % extra, pea gravel (1680)11.55 m³; 19.404 t
      28 US tons in 14-ton trucks2 loads
      Triangle base 20 ft, height 12 ft, 4 in crushed stone (1660)1.481 yd³; 2.073 US tons
      Reverse: 5 US tons of crushed stone (1660) at 4 in; 2 t of pea gravel (1680) at 5 cm289.5 ft²; 23.81 m²
      Depth typed as −4error on the field, no result

      Limits: it does not know your soil, drainage or traffic, and a gravel calculator cannot replace your quarry's gradation sheet.

      Common questions

      How many tons of gravel do I need for my driveway?

      Multiply length × width × depth to get the volume, add an allowance for compaction, and convert with the stone's density. A 60 × 12 ft drive built as 4 in of #3, 3 in of #57 and 2 in of pea gravel takes about 32.4 US tons; a 100 × 12 ft lane of road base laid 8 in loose takes about 48 tons.

      How much does a cubic yard of gravel weigh?

      Loose gravel usually weighs 1.4–1.7 US tons per cubic yard. Pea gravel is about 1.42, clean crushed stone about 1.40, crusher run and road base about 1.62, riprap about 1.85 and lava rock only about 0.74.

      How many square feet does a ton of gravel cover?

      At 1.4 tons per yard, one ton covers about 116 ft² at 2 in, 77 ft² at 3 in and 58 ft² at 4 in. Heavier road base covers less, roughly 100, 67 and 50 ft².

      How deep should gravel be for a driveway?

      A typical drive on firm soil has 6–9 in of stone in total, in layers: 3–4 in of #3, 2–3 in of #57 and 1–2 in of #8 or pea gravel on top. Soft soil and heavy trucks need more, and each compacted lift should be no thicker than about 6 in.

      How many tons are in a dump truck load?

      It depends on the truck and on local weight limits, so ask your hauler. I use 14 US tons as a starting value for a tandem and set the real capacity in the calculator, which then rounds the number of loads up.

      Should I compact gravel, and how much extra should I order?

      Compact every base layer. Order about 20 % extra for a plate-compacted crushed base and a third extra for dense-graded road base, which goes down 8 in loose and finishes at 6 in. Decorative top stone needs little or nothing.